Power Cable Break Emergency Repair

Power Cable Break Emergency Repair

Great Egg Harbor Bay, Ocean City, NJ
In January 2018, one of the power cables was determined to be damaged and in need of immediate repairs. As one of the most experienced local providers of this type of cable break service, Hydro-Marine Construction Co., Inc. was promptly retained to locate and repair the cable. Hydro immediately began coordination with the Coast Guard to allow for temporary blockage of portions of the channel in Great Egg Harbor, …Continue reading »

Posted in Projects |

Timber Fender Replacement and Jacketing

Timber Fender Replacement and Jacketing

Wildwood, New Jersey
Hydro-Marine Construction Co., Inc. (Hydro) was retained in late 2017 as a subcontractor to perform fender repairs at the bridge carrying Route 147 over Beach Creek near scenic Wildwood, NJ. The fender systems were being repaired as part of the remaining Hurricane Sandy related funding. The portions of the fender that projected beyond the bridge fascia could be easily removed and replaced. The portions under the bridge however, could not be easily replaced …Continue reading »

Posted in Projects |

Pier Rehabilitation

Pier Rehabilitation

Pier 217 North, Philadelphia, PA

In 2017, Hydro-Marine Construction Co., Inc. (Hydro) was retained as a subcontractor for the rehabilitation of Pier 217 North, located along the Delaware River just south of the Betsy Ross Bridge. The pier supports the outfall pipe for a sewerage treatment plant. The timber low deck structure exhibited areas of failure in the timber piles and caps, mostly at the outshore end, as well as miscellaneous spalls on the concrete seawall located in …Continue reading »

Posted in Projects |

Scour Protection Installation

Bridge Scour Protection at Sicklerville Rd (CR 536) Bridge over Great Egg Harbor River

Camden, NJ

In 2016 Hydro-Marine Construction Co., Inc. performed the scour protection repairs for the Sicklerville Road Bridge located in Winslow Township, NJ. The bridge is a single span bridge measuring approximately 50’x50 out to out. Stone riprap protection was installed in front of both abutments and extended in front of the wingwalls on either side of the bridge to the shoreline. Geotextile material and approximately 157 S.Y. …Continue reading »

Posted in News, Projects |

Bridge Pier Repairs and Jackets

Concrete Pier Repairs for Bridge S-31 (Oceanic Bridge) Bingham Avenue Over Navesink River

Middletown Township & Rumson Borough Monmouth County, New Jersey

Hydro-Marine Construction was awarded the contract for the installation of approximately 56 fiberglass pile jackets at Bridge S31 in 2016. The existing piles range in size and shape, mainly consisting of 20” to 22” reinforced concrete piles. The existing wrought iron collars and pile jackets need to be removed and the piles cleaned prior to installation of the new pile …Continue reading »

Posted in News, Projects |

DRWC Dredging Operations

Dredging Operations for 3 Marinas for Delaware River Waterfront Corporation

Piers 3, 5, & 9 Marinas, Philadelphia, PA

Hydro-Marine Construction Co., Inc. completed the dredging operations for the three locations on the Delaware River. The scope
of work was to dredge the areas to a bottom elevation of -5.0. An Ellicott Series 360 SL, Swing Ladder Dredge and DredgePack software were used for the dredging operations.

Pre and post dredge surveys were completed to ensure proper channel bottom elevations and to calculate the …Continue reading »

Posted in Projects |

Pier 68S Rehabilitation Design/Build

Pier 68S Rehabilitation Design/Build

Pier 68 South, Philadelphia, Pennsylvania

In 2015 The Castle Group provided the design/build services for the structural rehabilitation of Pier 68S. Pier 68 South is a timber low deck finger pier built in the 1930’s, located along the Delaware River in Philadelphia, Pennsylvania. In its original as-built condition, the pier extended into the river approximately 500 feet from the marginal bulkhead on the upriver side and approximately 470 feet from the marginal bulkhead on the downriver side. A …Continue reading »

Posted in Projects |

Bridge Pier Repairs and Jackets

Concrete Pier Repairs for Bridge S-31 (Oceanic Bridge) Bingham Avenue Over Navesink River

Middletown Township & Rumson Borough, Monmouth County, New Jersey

Hydro-Marine Construction was awarded the contract for the installation of approximately 56 fiberglass pile jackets at Bridge S31 in 2016. The existing piles range in size and shape, mainly consisting of 20” to 22” reinforced concrete piles. The existing wrought iron collars and pile jackets need to be removed and the piles cleaned prior to installation of the new pile …Continue reading »

Posted in Projects |

Pile Jacket Installation at County Bridge

Pile Jacket Installation at Canton-Greenwich Road Bridge Over Stow Creek

Cumberland County, NJ

In 2013, as part of the rehabilitation of the bridge, Hydro-Marine Construction Co., Inc. completed the installation of 70 pile jackets. Forty-Two  of the pile jackets were structural and twenty-eight  were protective jackets, each measuring 10 foot long. The extent of deterioration on the existing timber piles determined the type of jacket required. Both types of jacket were manufactured by Denso. The structural jacket consisted of a SeaShield Series 400 …Continue reading »

Posted in Projects |

Emergency Repairs at Ohio Avenue Bridges

Emergency Repairs At Ohio Bridges Structure Nos. 01AT-L01 & 01AT-L02

Atlantic County, NJ

In 2014, Hydro-Marine Construction Co., Inc. completed the repair of two bridges on Ohio Avenue which included repairs to the timber piles. Both bridges are constructed of timber pile pier bents with timber piles and retaining wall at the abutments. The bridges were immediately closed after W.J. Castle performed the routine underwater inspection of the bridges and found that several of the timber piles and bracing exhibited advanced decay and …Continue reading »

Posted in Projects |